Transnistria Conflict Resolution Task Force

Sector: Social

Implemented by: Carnegie Endowment for International Peace

Duration: August-November 2011

Budget: EUR 17,960

Partners: Project activities concluded.

Status: Project activities concluded.

Short description: Following Project Board approval, the project team succeeded to support an additional activity, implemented in September 2011 by the Carnegie Endowment for International Peace (CEIP). CEIP project “Transnistria Conflict Resolution Task Force” marked the launching of an effort to build and maintain a permanent “sustained dialogue” among experts interested in the Transnistrian issue.

Results: The participants considered that the first meeting of the Task Force was well organized and successful and appreciated the collegial atmosphere created by the staff at the Frankenwarte Academy in Wuerzburg. They called for similar meetings in the future, targeted toward specific fields related to the conflict